A can complete a project in 20 days and B can complete the same project in 30 days.

by
0 comment
Ask n AnswerA can complete a project in 20 days and B can complete the same project in 30 days.
Vinuthan S Staff asked 4 months ago

A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?

A. 18 days
B. 27 days
C. 26.67 days
D. 16 days
E. 12 days